|
Add the following:
“ However, in the
event of the Contractor not complying with the submission of
particulars within the times outlined above or the Engineer is not
satisfied with the particulars submitted, then in the event of
a)
the amount or nature of extra or additional work, or
b)
any cause of delay referred to in these Conditions, or
c)
exceptional adverse climatic conditions, or
d)
any delay, impediment or prevention by the Employer, or
e)
other special circumstances which may occur, other than
through a default of or breach of contract by the Contractor for
which he is responsible,
being such that in
the opinion of the Engineer to fairly entitle the Contractor to an
extension of Time for Completion of the Works, or any Section or
part thereof, the Engineer shall, after due consultation with the
Employer and the Contractor, determine the amount of such extension
and shall notify the Contractor accordingly, with a copy to the
Employer.
|